The Component Model Publishing - Milestone Settings enables monitoring of Flatplan workflow progress in the Publication Planner via the Next Milestone Date/Next Milestone Name and Traffic Light Name columns.
The model allows you to:
|
Milestone date and period / color configuration in Publication with Milestones component model |
||
|---|---|---|
|
Name |
Example Value |
Validation Type |
|
Publication Types defining milestone dates |
Publication |
|
|
Publication Types defining traffic lights |
Publication Group |
|
|
Workflow Start |
Start Date |
ISO Date and Time |
|
Milestone Date #01 Attribute |
Plan Page |
ISO Date and Time |
|
Milestone Date #02 Attribute |
Plan Approved |
ISO Date and Time |
|
Milestone Date #03 Attribute |
DTP Page Approved |
ISO Date and Time |
|
Period #01 |
Normal Period |
Number |
|
Period #01 Colour |
Normal Colour |
Regular Expression: [0-9a-f]{6} |
|
Period #02 |
Warning Period |
Number |
|
Period #02 Colour |
Warning Colour |
Regular Expression: [0-9a-f]{6} |
|
Period #03 |
Late Period |
Number |
|
Period #03 Colour |
Late Colour |
Regular Expression: [0-9a-f]{6} |
The other configuration option that effects the milestones is the definition of the working week. Unless modified the default setting is Monday to Friday from 09:00 to 17:00. Please contact Stibo if you need another definition of a working week. When entering the milestone dates for a publication it is advisable that they are set to be during working time.
The attributes that are configured in the Component Model 'Publishing - Milestone Settings' must have values on publication group, publication, or section level. The example below shows how the attributes might be configured for a particular publication.
|
Attribute values at a publication |
||
|---|---|---|
|
Attribute |
Example value |
Description |
|
Start Date |
2013-08-20 09:00:00 |
Tuesday |
|
Plan Page |
2013-09-02 09:00:00 |
Monday |
|
Plan Approved |
2013-09-10 09:00:00 |
Tuesday |
|
DTP Page Approved |
2013-09-20 09:00:00 |
Friday |
|
Normal Period |
100 |
If the remaining working time is 100% then... |
|
Normal Colour |
'green' |
... the traffic light is green |
|
Warning Period |
40 |
If the remaining working time is 40% then... |
|
Warning Colour |
'amber' |
... the traffic light is amber |
|
Late Period |
0 |
If the remaining working time is 0% then... |
|
Late Colour |
'red' |
... the traffic light is red |
The milestone and traffic light information shown in the Publication Planner for a given page is calculated in the following way:
Assuming that a publication has been created with the example dates and colors shown in the table above, and that the current time is Friday 2013-09-06 09:00:00, then this is how the traffic light colors would be calculated.
|
Flatplan page-workflow and traffic light status with current date/time 2013-09-06 09:00:00 |
|||
|---|---|---|---|
|
Page |
Workflow MILESTONE | Colour |
Explanation |
|
1 |
Plan page |
'red' |
The next milestone date is (Plan Page) 2013-09-02 09:00:00 The previous milestone date is (Start Date) 2013-08-20 09:00:00 The duration of the current task is therefore 8 working days The current date/time exceeds (Plan Page) 2013-09-02 09:00:00 by 6 working days. -6 as a percentage of 8 is -78% and so the corresponding color is 'red' |
|
2-3 |
DTP Page approved |
'green' |
The next milestone date is (DTP Page Approved) 2013-09-20 09:00:00 The previous milestone date is (Plan Approved) 2013-09-10 09:00:00 The duration of the current task is therefore 8 working days There are 10 working days from the current date/time until the next milestone date 10 as a percentage of 8 is 125% and so the corresponding color is 'green' |
|
4-5 |
Plan Approved |
'amber' |
The next milestone date is (Plan Approved) 2013-09-10 09:00:00 The previous milestone date is (Plan Page) 2013-09-02 09:00:00 The duration of the current task is therefore 6 working days There are 2 working days from the current date/time until the next milestone date 2 as a percentage of 6 is 33% and so the corresponding color is 'amber' |
2017, Stibo Systems